Request Phase

Request Phase

Description and Approach

This is the start of the project lifecycle. The Request shouldn't really be thought of as a "Phase" in the true sense. It is really just a defining point to formally capture the "Thinks... wouldn't it be nice to ...".

A Request could be for any of the following (ie, it will need to be classified initially):

  1. New Application System (or project)

  2. Major change to a legacy Application System

  3. Minor change to a legacy Application System

The only work performed during the Request phase is to complete the Request Form, receive it formally, record it in the Request Register, prioritise it and then decide if the next project lifecycle phase should be Phase Zero or Maintenance and Support. No project work is performed during the Request phase.

Requests could come from anywhere within the Enterprise, including from the IT Department itself. Requests could come in via any of the following IT Department Moment of Truth Activities:

  1. IT Help Desk

  2. IT Manager

  3. IT Information Centre

  4. Change Request Form

  5. Defect Report Form

  6. Additional Personal Computer

  7. Additional printer

  8. Branch relocation

  9. Application System access security change

  10. IT Account Manager

They are all treated the same.

Purpose and Objectives

To formally request some work be performed by the IT Department.

Why

  1. Formalises project initiation.

  2. Stops trivial requests taking up IT Department's valuable time.

  3. Everyone knows how to initiate a new project, project scope change or legacy Application System change.

Inputs

Standard (unmodified) Request Phase Work Plan.

Outcomes and Deliverables

The desired outcomes for this project lifecycle phase are:

  1. Someone is identified as having requested the work (the Engager).

  2. The request is initially classified.

  3. The request is prioritised.

The deliverables for this project lifecycle phase are:

Deliverable Producing Activity
Request Form (completed) Complete Request Form
Request Register (updated) Complete Request Form
Request Phase Work Plan Develop Request Phase Work Plan
Phase Zero Phase Work Plan (conditional) Develop Phase Zero Phase Work Plan
Maintenance and Support Phase Work Plan (conditional) Develop Maintenance and Support Phase Work Plan

Check Lists and Templates

New Project Proposal Form template

Project Priority Score Worksheet

Request Form template

Request Phase Work Plan template

Request Register template

Joint Application Design (JAD) Workshop

Not applicable to this project lifecycle phase.

Phase Work Plan

The Work Plan for this project lifecycle phase is documented in the Request Phase Work Plan.

Activities

Complete Request Form

Develop Request Phase Work Plan

Decide Next Project Lifecycle Phase

Plan and Attend Initial Request Meeting

Develop Phase Zero Phase Work Plan

Develop Maintenance and Support Phase Work Plan

Plan Phase Zero Interviews

Develop Phase Zero Questionnaire

Previous Phase

None.

Next Phase

If only a small amount of work is required, then the Request progresses to the Maintenance and Support project lifecycle phase.

If a project is required, then the Request progresses to the Phase Zero project lifecycle phase.

Duration

The Request project lifecycle phase is not performed in a Timebox so its duration may be shorter or longer than that indicated below.

30 elapsed minutes if the next project lifecycle phase will be Maintenance and Support.

0.5 elapsed day if the next project lifecycle phase will be Phase Zero.

Techniques Used

The following Techniques may be used during this project lifecycle phase:

8-7-6-5-4-3 Technique

Action Items

Body Language

Budgetting

Check Lists and Templates

Cost/Benefit Analysis

Impact Assessment

Interviewing

Managing Conflicts

Managing Expectation

Meeting Management

Negotiating

New Business Getting

Politics

Pragmatic Project Prioritisation Process

Requirements Management

Risk Management

Stakeholder Assessment

Stakeholder Management

Unresolved Issues

Participants

Engager

IT Maintenance and Support Manager

IT Manager

IT Systems Development Manager

Stakeholders

Technical Leader

Also See

You can print a "Phase Package" for this project lifecycle phase by clicking on the "Print" button (to print this topic to be used as a Table of Contents) then clicking on each of the Activities in turn. When the topic is displayed, click on the "Print" button, then click on the "Back" button to return to this topic and choose the next topic to print. When all Activities have been printed, follow the same procedure for each of the following topics.

During-Phase Activities

Generic Work Request Process

IT Department Processes

New Project Proposal Form

Phase Zero Confirmation Letter

Phase Zero Establishment Letter

Post-Phase Activities

Pre-Phase Activities

Project Priority Score Worksheet

Request Form

Request Phase Work Plan

Request Register